Key Points for Steel Structure Short Column Drawing

2026-02-10    173

1737339454425000.png

  1. Drawing Scale

    The scale must be adjusted in accordance with the architectural drawings before drawing; otherwise, the dimensions and figures may be illegible in the final printed drawings.
  2. Short Column Foundation Calculation
    The vertical reaction force of a single pile must be greater than 0. This can be achieved by enlarging the pile cap size or reducing the pile cap height while satisfying the punching shear requirements.
    If the above condition cannot be met, the pile uplift resistance shall be calculated.
  • Pile shaft bearing capacity and crack checking shall be conducted per Clause 5.8.7 of the Pile Foundation Code.
  • Pile foundation bearing capacity shall be calculated per Clause 5.4.5 of the Pile Foundation Code.
    For Class A and B foundation design grades, the uplift capacity shall be determined through on-site uplift static load tests.
  1. Pile Foundation Corrosion Consideration
    Attention shall be paid to the corrosiveness of the surrounding soil in pile foundation design.
    The design shall comply with:
  • Code for Anticorrosion Design of Industrial Buildings GB50046-95
  • Code for Construction and Acceptance of Building Anticorrosion Projects GB50212-2002